Last year, the company spent about six billion rubles, which was an excess of the plan by almost nine tens of millions of rubles. The funds were spent on work related to the maintenance of equipment at the TPP and TPP. As a result, more than eight dozen turbines were repaired, a huge number of boilers, generators and other technical elements were updated..
Due to the work carried out, the heating season was started in accordance with the established terms. At the same time, the preparation was completed one hundred percent. At the same time, SGK power plants during operation repeatedly reached their maximum load.
This year, the main work will be focused on three TPPs. In particular, it is planned to replace the heating surfaces of the boilers. At two more TPPs and one CHPP, it is planned to replace the elements related to the flow path. Turbine rotors will be repaired at two CHPPs.
The repair campaign for the current year has already begun. If it is successfully completed, preparatory measures will be implemented, which means that the provision of residents with energy without interruptions will be guaranteed..